Rzeszów Division of the General Management of the National Roads and Motorways (GDDKiA) has chosen the offer submitted by Polaqua, with the price of over 1.5 billion PLN, concerning the design and construction of a section of the S19 expressway between the Dukla junction (not including the junction) to Barwinek town (country border). The investment will include the construction of 15 elevated road sections, the longest of which is to be approx. 1.1 km long and will be suspended on pylons at the height of approx. 35 m, 10 bridges, 6 road overpasses, 6 animal crossings, and the Barwinek road junction. The approx. 18.2 km long route is to be put to use within 45 months (nearly 5 years). ■